New School
Building Progress.
Photos Taken Tuesday, February 6, 2007
| Photos taken by
Barrington Brennen. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
June 26, 2006
| Photos taken Sunday, June 26, 2006. The
secondary division walls are up and we are getting ready to pour
the belt course. Almost $1,000,000 US have been
spent so far. Give to this worthy project. |
 |
 |
 |
 |
 |
October 7, 2005
September 22, 2005
 |
 |
 |
 |
|
[ Sept 21, 2005 ]
The pouring of the floors for the Bahamas Academy New School
began at 10:10 a.m., Wednesday, September 21, 2005. Winston Ash
(pointing in right photo). VBA president, was all smiles as the
first truck delivered the cement. Many Adventist volunteers
came to assist in the pouring. |
 |
 |
 |
 |
|
[
July 22, 2005
] The new Bahamas Academy building on Marshall Road is
progressing well. The foundation is underway for the first
phase (the secondary school). These photos were taken on Friday
morning, July 22, 2005 by Barrington Brennen. Click on photos
to enlarge or download. |
April 28, 2005
Bahamas
Adventist Volunteers Start New School
|
The first digging
of the footing for the first phase of the New Bahamas Academy.
Photos taken Wednesday, April 27, 2005. Location: Marshall
Road near the Breath of Life Adventist Church. Click on
photos to enlarge |
|
 |
 |
 |
 |
|
Above photos taken on Wednesday, April 27, 2005. In photo on
bottom right: Left to right: Howard Barr, project assistant;
Cecil Cartwright, building consultant; Pastor Dannie
Clarke, Executive Secretary; Dr. Cheryl Rolle,
Director of Adventist Education; Pastor Leonard Johnson,
conference president; Winston Ash, VBA president;
Keith Major, Chairperson of the raising committee; Melvin
Lewis, conference treasurer; Pastor Andrew Burrows,
committee member. |
|